What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
A. ATP checks can be carried out automatically when releasing a production order.
B. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
C. ATP checks are used to evaluate the free capacity on a certain work center.
D. ATP checks are mandatory for lead-time scheduling.
E. ATP checks can be adjusted to also consider future requirements and receipts.