Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
B. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
C. Assign an appropriate availability checking rule to the material master for the product.
D. Activate the availability check and assign an overall profile in the production scheduling profile.