Which property applies for consumption with planning strategy 40 (planning with final assembly)?

Which property applies for consumption with planning strategy 40 (planning with final assembly)?
A. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
B. Consumption takes place with the planning material.
C. Consumption can reduce the total originally planned production quantity.
D. Consumption can increase the total originally planned production quantity.