What should the project manager do first when a team manager cannot deliver a product to the quality criteria specified in the product description?

What should the project manager do first when a team manager cannot deliver a product to the quality criteria specified in the product description?
A. Raise an off-specification
B. Raise a request for change
C. Raise an exception report
D. Raise a highlight report