Which is a purpose of the ‘controlling a stage’ process?
A. To produce a team plan for the work to be assigned to a team manager
B. To select and implement actions that will resolve deviations from a plan within tolerance
C. To obtain approvals for products delivered in a work package
D. To update a project plan to incorporate the actuals from a stage plan