When is the ‘controlling a stage’ process USUALLY first used?

When is the ‘controlling a stage’ process USUALLY first used?
A. At the end of the first stage after initiation
B. During the ‘starting up a project’ process
C. During the ‘initiating a project’ process
D. After the project board has authorized the project