Which process enables the organization to understand the work to be done to deliver the project’s products before committing to a significant spend?
A. Starting up a project
B. Directing a project
C. Initiating a project
D. Managing product delivery
Correct Answer: C
Explanation/Reference:
The purpose of the Initiating a Project process is to establish solid foundations for the project, so that the enabling organization understands the work to be done to deliver the project’s products before committing to a significant spend.Reference: https://www.prince2primer.com/prince2-initiating-a-project-ip-part-1/