Which is a minimum requirement for applying the plans theme?

Which is a minimum requirement for applying the plans theme?
A. The project must have at least two management stages
B. The team managers in the project must prepare team plans
C. Scope tolerance must be prioritized using MoSCoW
D. The project plan must be presented as a Gantt chart