Which is a minimum requirement for applying the risk theme?

Which is a minimum requirement for applying the risk theme?
A. Threats must be assessed for their impact on the viability of the project
B. A single role that is responsible for all risks must be defined
C. The PRINCE2 risk management procedure must be followed
D. Team managers must maintain their own risk registers