You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers.
Your customer’s major stakeholders identify significant changes that will increase the scope of a project.
Which two risk response strategies for the project definition update should you use? (Each correct answer presents part of the solution, Choose two.)
A. Exploit
B. Avoid
C. Enhance
D. Transfer
E. Share