The group that authorizes changes that must be installed faster than the normal process is called the?

The group that authorizes changes that must be installed faster than the normal process is called the?
A. Emergency CAB (ECAB)
B. Urgent Change Authority (UCA)
C. Urgent Change Board (UCB)
D. CAB Emergency Committee (CAB/EC)