You are using Microsoft Test Manager (MTM).
A test case is already in production.
You need to modify the test case to indicate it is being reworked.
What should you do?
A. Change the test case state to Design.
B. Change the test case to Blocked.
C. Change the test case state to Closed.
D. Change the test plan state to Inactive.
Correct Answer: A
Explanation/Reference:
No test cases are ready to be run.
When all test cases remain in a design state for a long time, some issue is blocking progress. You might want to investigate the cause of the blockage.
Note: Update the state of each test case as it progresses from Design to Ready to Closed.