Which three actions should you perform in sequence?

You are a software quality manager. Your company is using Microsoft Visual Studio to develop an application.
Your development team is almost finished with its first iteration. The testing team is preparing to verify that the product requirements are met.
You need to test the requirements.
Which three actions should you perform in sequence? To answer, move the correct actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place: