In a critical path analysis, if slack time in an activity exists, the activity:
A. Is not essential to the overall project.
B. Is a backup activity to replace a main activity should it fail.
C. Could be delayed without delaying the overall project.
D. Involves essentially no time to complete.
Correct Answer: C
Explanation/Reference:
Explanation:
Slack is the free time associated with activities not on the critical path. Slack represents unused resources that can be diverted to the critical path.