In PERT, slack is the:

In PERT, slack is the:
A. Uncertainty associated with time estimates.
B. Difference between the latest starting time and earliest finishing time.
C. Path that has the largest amount of time associated with it.
D. Number of days an activity can be delayed without forcing a delay for the entire project.