Home » IIA » IIA-CIA-Part3 » The numbers in the diagram are the expected times (in days) to perform each activity in the project.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.
The expected time of the critical path is:
A. 12.0 days
B. 13.0 days
C. 11.5 days
D. 11.0 days
Correct Answer: B
Explanation/Reference:
Explanation:
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Download Printable PDF. VALID exam to help you PASS.
|
|