How should the work be distributed between teams?

On a project where multiple Scrum Teams are working from the same Product Backlog, how should the work be distributed between teams?
A. The Scrum Team with the highest capacity will pull items from the Product Backlog first.
B. Each Scrum Team must have an equal amount of User Stories per Sprint.
C. The Product Owner separates the Product Backlog items for each team.
D. The Development Teams pull in work from a shared Product Backlog in agreement with the Product Owner and the other teams.