When does a Sprint end?
A. When there is no work remaining in the Sprint Backlog.
B. When the time-box expires.
C. It depends on the Product Owner.
D. Immediately after the conclusion of the Sprint Review.
When does a Sprint end?
A. When there is no work remaining in the Sprint Backlog.
B. When the time-box expires.
C. It depends on the Product Owner.
D. Immediately after the conclusion of the Sprint Review.
Typical mistake, I also have seen “retrospective” instead of “review” 🙂
“D2 ist for starting a new Sprint.
Should be ‘D’
Oh nevermind, B is right.