Home » Scrum » PSM II » Which is the best way to respond to Peter’s concerns?
Peter, a Project Manager, has raised concerns about your Scrum Team’s productivity and progress towards the objectives.
Which is the best way to respond to Peter’s concerns?
A. Share the Product Backlog, the projections towards the release dates and ensure that Peter has access.
B. Show the Profit & Loss (P&L) report.
C. Share the current impediments.
D. Share the last stakeholder status report prepared by the Scrum Master.
Correct Answer: A
Explanation/Reference:
Explanation:
One of the key pillars that support the empirical process control is Transparency. Transparency will help manage stakeholder expectations and allow the teams to effectively adapt if and when needed.