Which two scenarios would best represent a self-organizing Development Team? (Choose two.)
A. The Development Team members are strictly focused on the work within their functional role and always handing off the work to other roles in a timely matter.
B. Management works with the Scrum Master to optimize the Development Team’s progress during the Sprint.
C. Development Team members collaboratively select and re-plan their work throughout the Sprint.
D. The Development Team invites external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog.
E. The Development Team creates its own Sprint Backlog, reflecting all work that is part of the Definition of Done.