What should a Development Team do if it realizes it has selected too much work after starting the Sprint?

What should a Development Team do if it realizes it has selected too much work after starting the Sprint?
A. Modify the definition of "Done" to ensure all Product Backlog items can be done by the end of the Sprint.
B. Work with the Product Owner to remove some work or Product Backlog items as soon as possible.
C. Add additional team members to handle the extra work.
D. Continue working and update the Product Owner at the Sprint Review.

How To Pass PSM I Exam?

Scrum PSM I PDF dumps.

High quality PSM I PDF and software. VALID exam to help you pass.

How To Pass PSM II Exam?

Scrum PSM II PDF dumps.

High quality PSM II PDF and software. VALID exam to help you pass.

One thought on “What should a Development Team do if it realizes it has selected too much work after starting the Sprint?

  1. Is it necessary to remove PBIs from the Sprint Backlog?
    The commitment is only to the Sprint Goal, so even if some Items are incomplete, they can be added back to the Product Backlog during the Sprint Review and worked on in a future sprint; and so the Dev Team will learn how to plan better.

    So in which situation should the work be removed, and in which situation should the developers continue working as much as they can, and move the pending work back to the PB?