What must the Development Team do during the first Sprint?
A. Create a potentially shippable product Increment that includes at least one piece of functionality.
B. Analyze and estimate the requirements for the subsequent Sprints.
C. Create a project plan in order to map functional development to Sprint dates.
D. Only design and develop the architecture and infrastructure.
Correct Answer: A
Explanation/Reference:
Explanation:
Sprints promote iterative and incremental development.