The Development Team should have all the skills and competencies needed to:
A. Turn the Product Backlog items it selects into a potentially releasable product increment of functionality.
B. Do all of the development work in order to handoff to the testers in the subsequent Sprint.
C. Complete the project within the estimate as committed to the Product Owner.
Correct Answer: A