A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team.
Which three Scrum Values has the Development Team been neglecting? (Choose three.)
A. Commitment
B. Respect
C. Transparency
D. Focus
E. Openness
F. Courage
Correct Answer: BEF
Explanation/Reference:
Explanation:
The Scrum Team members have courage to do the right thing and work on challenging problems. The Scrum Team agree to be open (to speak and listen) about all the work and the challenges with performing the work. Scrum Team members respect each other’s skills, experience, and opinions.
How To Pass PSM I Exam?
Scrum PSM I PDF dumps.
High quality PSM I PDF and software. VALID exam to help you pass.
|
|
How To Pass PSM II Exam?
Scrum PSM II PDF dumps.
High quality PSM II PDF and software. VALID exam to help you pass.
|
|