Home » Scrum » PSM II » What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
A. Add the item to the bottom of the Sprint Backlog.
B. Replace an item in the current Sprint of equal size.
C. Add the item to the top of the next Sprint Backlog.
D. Inform the Product Owner so he/she can work with the person.
Correct Answer: D
Explanation/Reference:
Explanation:
Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow of value.