What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?

What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
A. Add the item to the bottom of the Sprint Backlog.
B. Replace an item in the current Sprint of equal size.
C. Add the item to the top of the next Sprint Backlog.
D. Inform the Product Owner so he/she can work with the person.

How To Pass PSM I Exam?

Scrum PSM I PDF dumps.

High quality PSM I PDF and software. VALID exam to help you pass.

How To Pass PSM II Exam?

Scrum PSM II PDF dumps.

High quality PSM II PDF and software. VALID exam to help you pass.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.