In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
A. enterprise environmental factors.
B. organizational process assets.
C. project management plan,
D. project funding requirements.