Home » PMI » CAPM » Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management
Correct Answer: B
Explanation/Reference:
Download Printable PDF. VALID exam to help you PASS.
|
|