What should be the concern?

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
A. There is a cost underrun.
B. There is a cost overrun.
C. The project may not meet the deadline.
D. The project is 20 days behind schedule.