Which is the correct formula for calculating expected activity cost for three-point estimating?

Which is the correct formula for calculating expected activity cost for three-point estimating?
A. Ce = (C0 + 6Cm + Cp)/4
B. Ce = (6C0 + Cm + Cp)/4
C. Ce = (C0 + 4Cm + Cp)/6
D. Ce = (C0 + C,,, + 4Cp) / 6