Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
A. Critical path method
B. Variance analysis
C. Schedule compression
D. Schedule comparison bar charts