Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
A. Define Activities
B. Direct and Manage Project Work
C. Develop Project Management Plan
D. Develop Project Charter
Correct Answer: D
Explanation/Reference:
Topic 3, Volume C