The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
A. adaptive
B. reflexive
C. predictive
D. iterative