Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
A. Resource breakdown structure
B. Staffing management plan
C. Project organizational chart
D. Scope management plan