Which process numerically analyzes the effect of identified risks on overall project objectives?

Which process numerically analyzes the effect of identified risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis