Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
A. Historical relationships
B. Dependency determination
C. Bottom-up estimating
D. Rolling wave planning