Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down