Which type of communication?
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication? A. Efficient B. Effective C. Push D. Pull
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication? A. Efficient B. Effective C. Push D. Pull
Which input provides suppliers with a clear set of goals, requirements, and outcomes? A. Procurement statement of work B. Purchase order C. Source selection criteria D. Bidder conference
An input to the Manage Project Team process is: A. Work performance reports. B. Change requests. C. Activity resource requirements. D. Enterprise environmental factors.
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives? A. Monitor and Control Project Work B. Perform Quality Assurance C. Close Project…
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations? A. Mandatory B. Discretionary C. Internal D. External
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as: A. Develop Project Team. B. Manage Project Team. C. Acquire Project Team. D. Plan Human Resource Management.
An input to the Plan Cost Management process is: A. Cost estimates. B. Resource calendars, C. The project charter, D. The risk register.
A technique used to determine the cause and degree of difference between baseline and actual performance is: A. Product analysis. B. Variance analysis. C. Document analysis, D. Decomposition.
An input to the Plan Stakeholder Management process is: A. The project charter. B. The stakeholder analysis. C. A communication management plan. D. A stakeholder register.
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project? A. Issue log B. Change log C. Expert judgment D. Change requests