Which of the following can be used to help you or other project managers on future projects?
Which of the following can be used to help you or other project managers on future projects? A. Sponsor B. Charter C. Stakeholder D. Documentation
Which of the following can be used to help you or other project managers on future projects? A. Sponsor B. Charter C. Stakeholder D. Documentation
After program closure, the lessons learned document becomes the part of ____? A. The risk register B. The company’s organizational process assets C. The program’s performance record D. The program charter
When is the lessons learned document updated? A. At closing phase B. At planning phase C. Throughout the project lifecycle D. At execution phase
What does CPI value less than 1.0 indicates? A. Cost overrun for work completed B. Scheduled performance is great C. Cost underrun of performance to date D. Cost for completed work is as per estimate
Which of the following is used to build consensus through rounds of anonymous surveys? A. The Pareto chart B. The Delphi technique C. The Monte Carlo simulation D. The Gantt chart
The ____ quality assurance technique ensures continuous improvement of all processes. A. Just-in-time management B. Ishikawa C. Six Sigma D. Kaizen
Which of the following represents the duration of activities against a calendar? A. Pie chart B. Scatter chart C. Gantt chart D. Pareto chart
____ is the degree to which a set of inherent characteristics fulfills requirements. A. Scope B. Project phase C. Regulation D. Quality
Small changes that bypass the organization’s change control procedures are called ____. A. Scope creep B. Lag C. Scope fault D. Gold plating
Which of the following documents is described in the statement below? "It is a type of procurement document used to request proposals from prospective sellers of products or services." A. Request for information B. Request for quote C. Request for…