What project management activity should happen in the GHW Project?

You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you’ve made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?
A. Quality audit
B. Scope verification
C. Scope control
D. Financial audit