Which of the following shows the ratio between a task’s budgeted and actual costs?

Which of the following shows the ratio between a task’s budgeted and actual costs?
A. To-Complete Performance Index (TCPI)
B. Schedule Variance (SV)
C. Schedule Performance Index (SPI)
D. Cost Performance Index (CPI)