What is this limit of resource hours in a time period known as?

You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?
A. Resource leveling heuristic
B. Resource requirements
C. Program risk
D. Resource utilization