What will the expected monetary value of the risk event be?

If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?
A. -$34,200
B. -$57,000
C. -9,500
D. You will need to know the utility function of the organization to determine this.