What is the schedule performance index (SPI) for this program?

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?
A. Negative ten percent
B. .75
C. $300,000
D. $225,000