What does CPI value less than 1.0 indicates?
A. Cost overrun for work completed
B. Scheduled performance is great
C. Cost underrun of performance to date
D. Cost for completed work is as per estimate
What does CPI value less than 1.0 indicates?
A. Cost overrun for work completed
B. Scheduled performance is great
C. Cost underrun of performance to date
D. Cost for completed work is as per estimate