What final item should you talk about before closing the meeting?

You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?
A. Discuss the importance of the project scope.
B. Thank everyone for attending.
C. Discuss the action items and the importance of the items being completed as planned.
D. Remind everyone that you’re the project manager if they have QUESTION NOs.