This is an example of what term?

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager’s project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project’s deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?
A. Gold plating
B. Errors and omissions
C. Expert judgment by the project manager
D. Value added change

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.