What is estimate at completion (EAC) for this program?

You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?
A. $2,656,500
B. There is not enough information to know.
C. $3,795,000
D. $1,035,000