Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they’re required to work on the program’s projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?
A. The schedule to complete the work will take longer.
B. The cost of the program and project will increase.
C. The risks of failure will increase.
D. The morale of the project managers will decline.