How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?
A. Monitor project stakeholder relationships using engaging strategies and plans
B. Send all project documents to stakeholders each time they are modified
C. Schedule monthly meetings with the stakeholders, including team members
D. Engage only with the project sponsors