With regard to a project manager’s sphere of influence in a project, which of the following does the project manager influence most directly?
A. Suppliers
B. Customers
C. Governing bodies
D. Project team
With regard to a project manager’s sphere of influence in a project, which of the following does the project manager influence most directly?
A. Suppliers
B. Customers
C. Governing bodies